The Kemess Project is on care and maintenance. Kemess is located in a highly prospective area within British Columbia’s prolific Golden Horseshoe, with multiple gold and copper discoveries. Kemess is a past producing mine which benefits from infrastructure already on-site, including a process plant, water treatment plant, air strip, and an open pit available for waste storage. In addition, Kemess has several permits in place and an impact benefit agreement with its First Nation partner. Confirmation and exploration drilling, as well as technical studies are under way, expected to provide an updated mining and processing concept which may unlock additional value. The previously studied Kemess underground block cave project is not a priority for Centerra’s pipeline at this time. The prior mineral reserves and resources estimate produced for this project was completed with costs and commodity price assumptions that are no longer applicable. As a result, the Company has applied current capital, operating and metal price assumptions to reclassify the historical reserves as a blend of open pit and underground resources.Centerra remains optimistic that Kemess could be a future source of gold and copper production.
The updated Kemess FS outlines a robust project with significant production of gold and copper over a 12 year mine life at low all-in sustaining costs. Importantly, the Kemess project hosts potentially material upside opportunities, including significant mine life extension opportunities associated with the large resource at Kemess.
Kemess is located in north-central British Columbia approximately 250 km north of Smithers and 430 km northwest of Prince George. The property is host to the former Kemess South (KS) Mine, the Kemess deposit and the Kemess East deposit. The Kemess deposit lies approximately 6.5 km north of the existing processing plant and other infrastructure.
The Kemess Mine comprised a large open pit mine feeding gold-copper ore to a 52,000 tonnes per day (t/d) processing plant. Between 1998 and 2011, Kemess produced approximately 3.0 million ounces of gold and 750 million pounds of copper from 218 Mt of ore. Open pit mining and processing ceased in March 2011 on depletion of the mineral reserves. The processing plant and other facilities and equipment that are required to support an underground mining operation at the Kemess deposit are currently under care and maintenance (Figure 1). Existing on-site infrastructure includes offices, warehouse, laydowns, maintenance facilities, a 300-person accommodation camp footprint, crushed ore stockpile and reclaim, access and service roads, airstrip, explosives magazines, and electrical sub-station. A Company-owned, 380 km power line originating in Mackenzie, provides power to the mine site via the BC Hydro grid.
The 107.4Mt Kemess ore reserve is located approximately 200 to 550 m below surface. The lateral extents (or footprint) of the ore reserve is approximately 570 m east-west and 90 to 300 m north-south (Figure 3). The planned production rate of 25,000 t/d (9.0Mt per year) is considered well within the capacity of a cave footprint with these dimensions and Kemess rockmass characteristics. Centerra has since obtained permits to increase throughput rates to 37,500 t/d.
According to SRK, “While all mining projects have residual technical uncertainties, the Kemess Project is considered to be relatively low risk for a caving project in terms of key mining-related risks including production ramp-up, drawpoint stability, subsidence and mudrush.”
Following extraction from the Kemess cave and primary crushing underground, ore will be conveyed to the existing process plant where it will be processed at an average rate of 25,000 t/d (9.0Mt per year) using existing grinding, flotation, thickening and concentrate handling facilities. Concentrate will be trucked to the AuRico-owned load-out facility in Mackenzie for subsequent rail transport to market. Testwork indicates that Kemess ore will produce a concentrate that is free of deleterious elements and readily marketable to both smelters and traders.
Waste rock and tailings from the mining and processing of Kemess ore are planned for deposition in the Kemess open pit which received tailings late in the operation of the Kemess mine.
The Kemess FS report has been prepared by SRK Consulting (Canada) Inc (SRK) with contributions from AuRico, AMEC Foster Wheeler, BioteQ Environmental Technologies, Conveyor Dynamics, ERM Consultants Canada, Exen Consulting Services, KWM Consulting, Mine Ventilation Services, and Struthers Technical Solutions.
(1) Co-product basis allocates costs proportionally based on the relative value of gold and copper revenues while by-product basis applies all copper and silver revenues as a credit to costs
(2) All-in Sustaining Cash Costs (AISC) defined per World Gold Council guidelines but excl. corporate G&A allocation
The Kemess panel cave design and schedule was derived using Geovia’s Footprint Finder and PCBCTM software, an industry standard for cave optimization and scheduling, using the resource model provided by SRK. Figure 4 shows the resulting annual gold equivalent production profile.
Given local topography, the cave footprint will be accessed and supported by a triple decline system comprising access, ore conveying and intake air declines. Mine levels within and directly adjacent to the cave footprint comprise undercut, extraction, conveying and ventilation levels. Total life of mine development requirements are estimated to be 47,750m lateral and 2,200m vertical development, with all lateral development assumed to be carried out by owner crews. Lateral development peaks at 8,500m in the 4th year of mine development, and averages 5,300m over the nine year period during which underground development takes place. A total 2,250t of ore per metre of lateral development results from this mine design, representing a very high “development efficiency” compared to other underground mining methods. Note, that panel caving differs from block caving in that panel caving does not require all cave footprint development to be completed ahead of cave initiation.
Cave ore is fed from the undercut level to the extraction level via a total of 582 drawpoints (291 drawbells), facilitating average steady-state production of 25,000 t/d or 9.0Mt per year. Caving will be initiated in the highest value ore at the east end of the Kemess deposit. Ore will be delivered to one of four primary jaw crushers located on the south side of the extraction level. Following crushing, ore will be conveyed by one of two transfer conveyors to a 3.2km long underground conveyor (in the conveyor decline) and then transferred to a 4.9km surface conveyor that will deliver ore to the existing stockpile ahead of the process plant.
Geotechnical assessment for caveability, fragmentation, subsidence and ground support was carried out by SRK and Itasca Consulting Group Inc. using both empirical and numerical modeling methods, with this work carried out as part of the 2013 Kemess FS (SRK, 2013).
Processing ore at a rate of 9.0Mt per year will be achieved using one of the two grinding circuits that was used to process ore. The original flotation, thickening and concentrate handling facilities will be used for processing Kemess ore. Tailings will be pumped to and stored in the open pit, with sufficient capacity for a minimum 107.4Mt ore treated in the process plant. The open pit was used for waste rock and tailings storage towards the end of the operation.
Testwork has resulted in estimated metallurgical recoveries of 91% copper, 72% gold and 65% silver.
For the Kemess ore, the process plant is expected to produce a single concentrate with an estimated 22% copper content as well as payable gold and silver. Testwork has shown the Kemess concentrate to be free of deleterious elements, hence it is not expected to incur penalties and it is expected to be readily marketable to both smelters and traders.
Due to minor mineralogical differences between the Kemess and historical ores, a finer grind is required for Kemess ore, resulting in the requirement to install stirred regrinding mills to achieve the targeted P80 20 microns. Testwork carried out to determine fine grinding mill energy requirements included batch Eliasaon, Levin and Signature Plot tests.
The majority of the capital expenditures at Kemess pertain to underground mine capital, reflecting the benefit of having existing infrastructure and processing facilities in place, but also the higher proportion of up-front development requirements for cave mining. The two most significant categories of mine capital expenditures are underground mine development and the purchase of underground mobile equipment. While the outright purchase of underground mining equipment is assumed for this study, AuRico will also be evaluating leasing alternatives. Pre-commercial production expenditure on underground mobile equipment totals C$86M or 19% of initial capital.
Pre-production capital expenditures are estimated at C$524M comprising C$380M in initial capital expenditures and $144M in capitalized operating expenses. A further C$70M in capital expenditures and C$9M in capitalized operating expenses (net of pre-commercial production revenue and after adjustments for working capital and taxes) will be spent before commercial production is declared (refer to Table 1). The total pre-production capital expenditure equates to C$603M or US$452M. The development period is 4 years to first production and 5 years to commercial production.
Pre-production capital is inclusive of 12.5% contingency. It is estimated that 87% of capital expenditure will be C$ denominated, with the 13% non-C$ denominated costs relating to equipment (including spares), consumables and fuel purchases.
Sustaining capital expenditure is approximately C$262M, including C$207M of ongoing underground development and underground mobile equipment refurbishments and replacements, C$31M relating to the tailings storage facility, and C$13M for the addition of a third fine re-grind mill in the processing facility.
Table 1: Initial Capital Cost Estimate (C$ millions)
The total unit operating costs after the commencement of commercial production are estimated at C$14.27/t ore, comprising a mining cost of C$5.39/t, a processing cost of C$5.69/t, a G&A cost of C$2.93/t and a water treatment cost of C$0.26/t. A summary of the Kemess life-of-mine (commercial production period) unit operating cost estimates are shown in Table 2.
Labour is a significant component of operating costs, comprising 53% of mining, 17% of processing, and 26% of G&A costs.
Other significant operating costs include consumables (37% of processing cost), electricity (32% of processing cost), and flights and camp (28% of G&A cost).
It is estimated that 85% of operating costs will be C$ denominated, with the 15% non-C$ denominated costs due to equipment spares, consumables and fuel purchases.
Table 2: Operating Expenditure Estimate – Summary of Unit Costs (C$/t ore)
Marketing expenses include treatment and refining costs, smelter deductions and transportation costs. Various alternate destinations were studied and compared for the most favourable combination of freight costs and economic terms. For the Kemess FS, it was assumed that concentrate would be exported to a smelter in Japan, Korea or Northern China.
Total life-of-mine concentrate transport costs are estimated at C$208M, or C$176 per dry metric tonne, with approximately 75% being Canadian dollar denominated expenditures.
Total life-of-mine treatment and refining costs are estimated at C$196M, comprised primarily of treatment charges of US$80 per dry metric tonne of concentrate, and refining costs of US$0.08 per payable pound copper and US$6.00 per payable ounce of gold; these costs are entirely US dollar denominated.
Total life-of-mine effective payable rates are 95.5% copper, 97.0% gold and 90.0% silver, for total smelter deductions of C$161M.
No penalties have been applied as testwork has shown the Kemess concentrate to be free of deleterious elements.
See Full Mineral Reserves and Mineral Resource Table
This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.
Strictly Necessary Cookie should be enabled at all times so that we can save your preferences for cookie settings.
If you disable this cookie, we will not be able to save your preferences. This means that every time you visit this website you will need to enable or disable cookies again.
This website uses Google Analytics to collect anonymous information such as the number of visitors to the site, and the most popular pages.
Keeping this cookie enabled helps us to improve our website.
Please enable Strictly Necessary Cookies first so that we can save your preferences!